
When Does Your Solar Project Need to Follow Power Plant Rules? Understanding Critical Regulatory Thresholds
As solar energy projects grow in scale, they can cross regulatory thresholds that require them to be treated as power plants. Understanding these critical junctures—typically at 20 MW, 5 MW, and 2 MW—is essential for developers to navigate the complex web of requirements governing grounding design, project timelines, and operational compliance. This blog post will demystify these thresholds and explain when your solar project needs to adhere to power plant rules.
As solar energy projects grow in scale, they can cross regulatory thresholds that require them to be treated as power plants. Understanding these critical junctures—typically at 20 MW, 5 MW, and 2 MW—is essential for developers to navigate the complex web of requirements governing grounding design, project timelines, and operational compliance. This blog post will demystify these thresholds and explain when your solar project needs to adhere to power plant rules.
### The 20 MW Threshold: FERC Jurisdiction and GSU Transformers
Once a solar project reaches 20 megawatts (MW) or more, it typically falls under the jurisdiction of the Federal Energy Regulatory Commission (FERC). At this scale, the project is considered a significant power-generating facility, and its impact on the grid is substantial enough to warrant federal oversight. A key technical requirement at this level is the mandatory use of a Generator Step-Up (GSU) transformer. The GSU steps up the voltage from the solar inverters to the high voltage required for transmission to the grid. This requirement has major implications for the project’s grounding and electrical design, as the GSU transformer creates a new, separately derived system that must be grounded in accordance with specific utility and federal standards.
### The 5 MW Threshold: Medium-Voltage Collection Systems
For projects at or above 5 MW, a medium-voltage (MV) collection system is almost always required. This system gathers the power generated by the solar arrays and transmits it to a central point, typically a substation, before it is delivered to the grid. The introduction of an MV system means that the project must comply with more stringent grounding and safety standards to manage the higher voltages involved. This includes requirements for equipment grounding, substation grounding grids, and often, detailed ground-fault protection schemes. The design and implementation of these systems require specialized engineering expertise to ensure the safety and reliability of the project.
### The 2 MW Threshold: Increased Scrutiny from Utilities
Even at the 2 MW level, solar projects often face increased scrutiny from local utilities. While not typically subject to FERC regulations, these projects are large enough to have a noticeable impact on the local distribution grid. Utilities will often impose specific interconnection requirements, including those related to grounding, to ensure that the project does not compromise the stability and safety of their systems. These requirements can vary widely from one utility to another, so it is crucial for developers to engage with the utility early in the design process to understand their specific standards.
### Conclusion
Navigating the regulatory landscape for solar projects requires a clear understanding of the critical thresholds at which different rules and requirements come into play. From the federal oversight and GSU requirements at 20 MW, to the medium-voltage systems at 5 MW, and the utility-specific standards at 2 MW, each threshold brings a new layer of complexity to the project. By being aware of these junctures, developers can better plan their projects, anticipate design challenges, and ensure a smoother path to commissioning and operation.
Related Articles

The Grandfathering Myth: What Older Substations Must Know About 29 CFR 1910.269
If you operate or maintain an older substation, you may have heard the term "grandfathered" tossed around when discussing OSHA compliance. Perhaps you've been told that because your facility was built decades ago, it doesn't need to meet current 29 CFR 1910.269 requirements—especially the grounding provisions in section (n) and Appendix C Part III. Unfortunately, this common assumption could be putting your workers at serious risk and your organization in regulatory jeopardy.
Read article
Understanding IEEE 80: The Foundation of Substation Grounding Safety
IEEE 80 is the definitive standard for the design of grounding systems in AC substations. This article explains the key concepts, including tolerable body current limits, step and touch voltage criteria, and the role of soil resistivity in grounding design.
Read article
How to calculate fault current in electrical substation grounding design?
Milan asked: How do I calculate the fault current an electrical substation grounding design? I am trying to understand how to design a substation grounding system and fault current is something I am not getting. For example, for a small substation with some transformers, if there is a fault in the system how will the fault current flow into the grounding system?
Read article